Every development lender asks the same two questions before anything else: what will the project cost, and what will it be worth when it is finished. Those two numbers, total development cost (TDC) and gross development value (GDV), set the size of the loan.
What TDC includes
TDC is everything it takes to deliver the project:
- Land, including stamp duty and acquisition costs
- Construction, under the building contract
- Professional fees: architect, engineers, town planner, quantity surveyor, project manager
- Council contributions, authority fees and statutory charges
- Marketing and selling costs
- Finance costs, including capitalised interest and lender fees
- A contingency, usually expected by the lender and checked by their quantity surveyor
Lenders will rebuild your TDC from their own reports. If your feasibility leaves out interest or understates contingency, the loan will be sized on their higher number, and the equity gap will be bigger than you planned.
What GDV means
GDV is the total value of the finished product, net of GST where it applies. For a townhouse project it is the sum of the expected sale prices. For a project you plan to hold, such as industrial or build-to-rent, it may be the as-if-complete valuation instead.
GDV comes from the lender’s valuer, not your agent’s appraisal. The valuer will look at comparable sales and any presale contracts.
The two tests
A senior lender applies both tests and lends the lower of the two:
- Loan to cost (LTC): a maximum percentage of TDC. Senior debt commonly runs to around 75% of cost.
- Loan to value (LVR on GDV): a maximum percentage of GDV, commonly somewhere in the 60% to 70% range for senior debt depending on the lender and the asset.
The cost test protects the lender if the project overruns. The value test protects the lender if the market softens before the stock is sold.
A worked example
| Amount | |
|---|---|
| Land and acquisition costs | $6.0m |
| Construction | $11.0m |
| Fees, contributions, interest and contingency | $3.0m |
| Total development cost | $20.0m |
| Gross development value | $26.0m |
- 75% of TDC = $15.0m
- 65% of GDV = $16.9m
- Senior loan = the lower, $15.0m
- Equity required = $20.0m less $15.0m = $5.0m
If the developer only has $3.0m of equity, there is a $2.0m gap. That is the role of mezzanine or stretch senior finance: taking total debt to around 85% of cost, in this case $17.0m.
What this means for your feasibility
- Margin matters as much as cost. In the example, the project shows a $6.0m margin, 30% on cost. A thinner margin pushes the GDV test closer to binding and reduces what lenders will offer.
- Get the GDV right early. An optimistic GDV in your feasibility does not change the lender’s valuation. Model with a conservative number.
- Interest is part of cost. Capitalised interest increases TDC, and therefore the equity needed. Longer programmes cost more equity, not just more interest.
If you would like us to run your numbers through both tests, send us the feasibility.