How construction loan progress draws work

Construction finance is released in stages, not as a lump sum. How progress draws, quantity surveyor certification and cost to complete work in practice.

A construction loan is not paid out on day one. It is released in progress draws as the build advances, so the lender is never funding more than the work completed on site.

The usual sequence

  1. Land and early costs. At financial close, the facility typically refinances the land loan and funds approved upfront costs.
  2. Equity first. Most lenders require the developer’s equity to be spent before the loan funds any construction. This is often called equity in first.
  3. Monthly claims. The builder submits a progress claim, usually monthly, for work completed.
  4. QS certification. The lender’s quantity surveyor inspects the site and certifies the value of work done.
  5. Payment. The lender pays the certified amount, usually directly to the builder.
  6. Retention. A portion may be held back until practical completion and defects are resolved.

Cost to complete

Before each draw, the lender’s quantity surveyor checks that the remaining loan is enough to finish the project. If costs have increased and the undrawn facility no longer covers them, the lender can stop funding until the shortfall is filled, usually with more developer equity.

This is the single most common cause of stalled projects. A cost overrun of a few percent can freeze the facility at the worst possible time.

How to avoid delays

  • Carry a realistic contingency. It protects the cost-to-complete test.
  • Use a fixed-price building contract where possible. Lenders prefer them because they limit overrun risk.
  • Keep variations under control. Every variation changes the cost to complete.
  • Submit claims cleanly. Missing invoices or statutory declarations delay certification and payment.

When a project stalls

If a facility has frozen because of an overrun, the options are new equity, a top-up from the existing lender, or a refinance into a new facility sized to the remaining programme. In our Moreton Bay industrial transaction, new construction funding reset the capital stack on a stalled build without further sponsor equity.

Send us the project if a draw has stopped or you can see an overrun coming.